A road is only as strong and durable as its base . . . and the stability of the road depends on the proper interlocking of the aggregate. Calcium chloride:
|
Town of Caledon Trial and method of
application: General Chemical contracted Trow Inc. to select the test and control sites and to perform all the testing before and after reclamation. Trow engineers designated a 150 m (164 yd.) stretch of Chinguacousy Road as the test section. Across a 20 m (22 yd.) buffer zone to the north of the test section, engineers staked out another 150 m (164 yd.) control section. Both sections were rehabilitated but no calcium chloride was added to the control section. Soil samples were taken at staggered intervals from both the test section and the control section before and after pulverization. Testing of the existing subgrade soil found clayey silt to silty clay till. The granular was a mixture of sand and gravel, predominantly hard carbonates generally varying in thickness from 220-300 mm (9-12 in.) The bituminous surface of the road was a heterogeneous mixture of hot mix asphalt and surface treatment of a uniform thickness of 60-80 (2.5-3 in.). The reclamation work was contracted out but all
other work was done by the Town. The test and control sections were reclaimed
between August 9 and 11, 1989 using the following procedures, Stabilizing
a road with calcium chloride consists of 7 steps: |
Step 1 Scarification of road surface: Pulverize the existing bituminous surface with the underlying granular to a design depth of approximately 150 mm (6 in.) using one pass of a Reclamer 1 PulviMixer. |
Step 2 Addition of aggregate: Place additional imported gravel granular base course to the test section and control section using end-dump and belly-dump methods, and apply water using tanker truck with spray bar attachment to achieve suitable moisture conditions. The total average additional granular thickness was approximately 50 mm (2 in.) after grading and shaping; |
Step 3 Application of calcium chloride: Apply liquid calcium chloride to the test section granular base at a rate of 3.6 liters per square meter (.75 gallon per square yard) 35 percent solution. |
Step 4 Mixing of materials: Mix the loose granular and calcium chloride with one pass of a Reclaimer 1 Pulvi-Mixer. |
Step 5 Shaping and cross section: Grade and shape the full road width to restore crossfall. |
Step 6 Compaction of surface: Compact loose granular using a single steel drum vibratory compactor.
|
Step 7 Seal surface with calcium chloride Spray compacted granular surface of roadway with liquid calcium chloride at a nominal rate of 1 liter per square meter (.25 gallon per square yard). The total volume represents approximately 1 percent calcium chloride by weight of dry aggregate weight for 150 mm (6 in.) layer thickness. The road was then left open to traffic for three weeks before the Town applied a double surface treatment of stone chips and emulsion. |
|
Other Reports |
|
THE CALCIUM CHLORIDE EXPERTS